Project Name: Soil-Improvement-of-Fao-Tank-farm-Project-(EC)
Employer : Interlink Constructions Co.
Owner: South Oil Co.
Client: Ibn Majid Co.
Location: Fao-Basra-Iraq
Type of Contract: EPC
Progress: Mobiliziation
Project Description:
Designs &Construction of:
The objective of the work is to design and execution of a ground improvement scheme for the project site based on Soil Mixing Method.
Volumes:
- Around 5,000 Soil Mixing Columns with the depth up to 30 meter.
- More than 95,000 cubic meter of Soil Mixing
- More than 90,000 cubic meter of Excavation works